London's data-centre power demand
Operating demand beside the capacity already requested from the electricity grid.
Data access
Use the machine-readable JSON record or the flattened CSV download or the compact Markdown version.
Methodology
The GLA reports 99 operating sites delivering around 760 MW and a grid connection queue around ten times current capacity. The queued value is therefore shown as an approximate 7,600 MW derived estimate: it is requested capacity, not consented, built or inevitable demand.
Provenance
- Source
- Greater London Authority
- Cadence
- irregular
- Engine
- comparison
- Licence
- Open Government Licence v3.0